tugas KE-4 rekayasa jalan raya I

TUGAS REKAYASA JALAN RAYA I
NAMA : YUNIARTA RAGA S.N
NPM : 0953010012

X
Y
1
1.26
3
3.12
5
5.42
7
7.22
9
8.62
11
6.12
13
4.32
15
2.12
17
1.72












Jika ongkos pengerukan Rp. 250.000,00 per  m². hitung biaya total?

A = ½ x 2 [1.26 + 2 (3.12 + 5.42 + 7.22 + 8.62 + 6.12 + 4.32 + 2.12 ) + 1.72

A = 76.86 m²

biaya total = 76.86 x Rp. 250.000,00 = Rp. 19.215.000,-
 